Great Lakes Coastal Forecasting System (GLCFS) Status Page
Fri May 9 19:27:04 GMT 2008

 

0Z NOWCAST
Process Start Time End Time Status
Acquire NOAAPORT Obs 01:19 01:19 Completed 01:19
Model Runs 01:20 01:21 Completed 01:24
Graphical Products 01:21 01:22 Completed 01:26
Update Web Page 01:22 01:23 Completed 01:28
12Z NOWCAST
Process Start Time End Time Status
Acquire NOAAPORT Obs 13:19 13:19 Completed 13:19
Model Runs 13:20 13:21 Completed 13:22
Graphical Products 13:21 13:22 Completed 13:24
Update Web Page 13:22 13:23 Completed 13:27
6Z NOWCAST
Process Start Time End Time Status
Acquire NOAAPORT Obs 07:19 07:19 Completed 07:19
Model Runs 07:20 07:21 Completed 07:22
Graphical Products 07:21 07:22 Completed 07:24
Update Web Page 07:22 07:23 Completed 07:26
18Z NOWCAST
Process Start Time End Time Status
Acquire NOAAPORT Obs 19:19 19:19 Completed 19:19
Model Runs 19:20 19:21 Completed 19:22
Graphical Products 19:21 19:22 Completed 19:24
Update Web Page 19:22 19:23 Completed 19:27

 

0Z FORECAST
Process Start Time End Time Status
Acquire & Process ETA12 02:47 02:47 Completed 02:32
ETA Products 02:47 02:47 Completed 02:33
Model Runs 02:47 02:56 Completed 02:47
Graphical Products 02:56 02:58 Completed 02:49
Update Web Page 02:58 02:60 Completed 02:50
12Z FORECAST
Process Start Time End Time Status
Acquire & Process ETA12 14:45 14:45 Completed 14:32
ETA Products 14:45 14:45 Completed 14:33
Model Runs 14:45 14:55 Completed 14:47
Graphical Products 14:55 14:57 Completed 14:49
Update Web Page 14:57 14:58 Completed 14:50

Note 1: Start and End Times represent averages over most recent 14 days.
Note 2: Status times represent completion time of most recent run.